Siding was finished in October and November which entailed caulking and painting until the weather stopped us. Only one window and one piece of trim did not get painted, but we're happy with the progress. The closed cell wall insulation was complete Mid-October and flat ceiling battens were installed the first week of November. The window jambs were foam filled following that to finish the 2nd building permit. During that time the construction crew of Cherie and Mike took a well deserved trip to Mexico for a week of rest and relaxation with Steve and JoNell. The Driveway was installed to the 2 car garage the week before Thanksgiving.
During the fall family members Mom, Steve, JoNell , Cousin Diane, Cousin Jen and Scott helped paint and suck-up 5 acres of leaves (see photos of the leaf free rear yard).
Drawing for the interior permit has been finishing up during the month of December with a planned sumbittal date of 12/29/10. Septic Engineer Al Schmitt laid out the troubled new septic field design. Either the water table was too high or soil conditions were not acceptable. Field is going to be a chamber system which is a more efficient septic design, but not recognized by the county (so reduction of length not given). Backup sump pump has been successfully installed (in case of a reoccurring ground water problem) and the furring framing has been started to increase the wall thickness from 2"x 4" to 2" x 6" to accomodate the R-27 wall insulation. Mike and Dave Baum have been trying to get the existing high-efficiency furnace running over the last week and make progress with every part replacement.
Our new completion date has been moved back to April 1st,2011.
